This article is for general information only and is not legal advice. It reflects the position as at 17 November 2026. Please seek advice on your specific circumstances.
Why the rules are tightening
Thailand has become one of the region's most sought-after data-centre locations, and demand is putting pressure on the grid. Officials report that more than 110 applicants have asked for electricity totalling over 30,000 MW, much of it overlapping. On 10 November 2026, Cabinet endorsed a national framework, prepared by the Data Centre Operations Policy Committee, that sets out how such projects will be assessed and approved.
Seven tiers by power demand
Projects are classified by power demand: below 0.5 MW; 0.5 to under 5 MW; 5 to under 10 MW; 10 to under 20 MW; 20 to under 50 MW; 50 to 200 MW; and above 200 MW. Oversight applies from 0.5 MW.
Location follows the tier. Facilities under 20 MW may be in commercial zones. Facilities of 20 MW or more must be in industrial estates.
Screening comes first
Applications submitted after 14 August 2026 must pass an economic-value assessment by a central screening committee before the BOI, the electricity utilities or building-permit authorities can approve them. Financial security requirements are intended to filter out applicants that are not serious about building.
Existing projects and transition
Projects that received BOI promotion or construction permits before 14 August 2026 can go ahead, but they have one year to meet new minimum environmental standards. All approved projects will also be reviewed through a new data-centre One Stop Service.
What comes next
- A draft law, prepared by the Ministry of Digital Economy and Society, requiring operators to register on a national data-centre dashboard (TH-DC).
- Revised rules to support the One Stop Service, plus minimum technical standards for data centres, with enforcement expected after about a year.
- Electricity and water tariffs for data centres that reflect their full direct and indirect costs.
- Zoning plan amendments, which officials estimate will take 8 to 12 months.
What to do now
- New investors: allow for screening in your project timeline and prepare evidence of economic benefit, such as local jobs, local components and green energy use.
- Choose sites with the tier in mind. Projects of 20 MW or more need industrial estate land.
- Existing BOI-promoted operators: check your promotion and permit dates against 14 August 2026 and plan how to meet the environmental standards within one year.
- Landowners and developers: confirm zoning and building permit status before committing to data-centre leases.
- Watch for the registration law and the technical standards as they are drafted.
How SBC can help
SBC advises foreign investors on BOI promotion applications and conditions, Foreign Business Act structuring, land and industrial estate arrangements, and the licensing steps for data-centre and digital infrastructure projects.
Contact us at info@sbcinterlaw.com to discuss how these changes affect your business.
Request a consultationLegal references
- Cabinet Resolution of 10 November 2026 endorsing the policy on data-centre business operations
- Investment Promotion Act B.E. 2520 (1977), as amended
- Building Control Act B.E. 2522 (1979)
- Town Planning Act B.E. 2562 (2019)
- Industrial Estate Authority of Thailand Act B.E. 2522 (1979)
This article reflects information available as at 17 November 2026. Publication date: 28 November 2026.
The information on this website is general in nature and is not legal advice. It may not reflect the latest legal developments and should not be relied on for any specific situation. Using this website does not create a lawyer–client relationship. For advice on your own circumstances, please send us an enquiry at info@sbcinterlaw.com. Read the full disclaimer.